ELECGAS, SIEMENS

Combined Cycle Power Plant Pego 830MW

Cycle Combined Power Plant (830MW) in Pego (Portugal). Composed by a 2 Turbine building, 2 Recovery Boiler, 2 tower refrigeration, installations racks, transformers and auxiliary buildings of gas compression, water treatment, Stores and office building.

Project Details
Pego, Portugal
Starting date: November 2.008 – Foreseen completion date: February 2.011

Surface of action: 46.000 m²

Volume of Concrete: 26.000 m³

Corrugated steel: 3.400 Tn

Steel structure: 2.500 Tn

Cladding closings “sandwich in situ”:16.000 m²